|
|
|
|
|
|
|
|
|
|
|
|
|
CFHTLS:
Reinstatement of the Very Wide component |
|
|
|
|
|
|
|
Joint Canada-France proposals |
|
|
Decommissioning
of MOS and Gecko |
|
|
|
The meeting was attended
by SAC members Pierre-Alain Duc (Vice-chair), L. Ferrarese, C. Ftaclas, J. F. Gonzalez,
C.
Gry, H. Hoekstra, R.
Jedicke, G. Mitchell, P. Petitjean, N. St-Louis (Chair).
The CFHT Director C. Veillet as well as P. Martin and D. Salmon,
participated
in presentations and discussions.
|
Derrick
Salmon reported on the technical activities of this semester. The new
air dryer
system has been successfully re-installed and is working well since
March 2006.
The departmental permit for grounding grid repair has been received but
it has
not yet been sent to the Office of Mauna Kea Management because a
request to
add a new OHANA fiber optic conduit under the roadway will be added to
the
document. Another above ground conduit for OHANA is planned on CFHT and
Gemini
subleases. Work on the observatory’s
building air handler is continuing and an investigation of the
facility’s
electrical power consumption has been conducted in an effort to
identify the
largest contributors and eventually save energy.
SAC
was informed that CADC has agreed to continue providing the Poopsy
software for
proposal submission. Also, the mirror will not be re-aluminized next
summer as
planned; there is only a small amount of degradation, which has a very
small
impact on image quality. The mirror will thus be re-aluminized during
the
summer 2007.
MegaPrime
Technical failures of the camera are still
occurring regularly but the staff is becoming increasingly
knowledgeable about
them and the time spent on repairs is decreasing. The pulse
tube/rotating valve
cryogenic system is the most troublesome.
The fibre optic connectors are very unstable and the staff
always has to
be extremely careful when manipulating them. Improved technology is
being
looked into. There have also been some small problems with the SLINK
communication system and with the jukebox/filter changer.
Following the July
2005 meeting
between CEA and CFHT, it was agreed that both parties would evaluate in
detail
the potential repairs or re-design of some systems in the camera and
decide on
a course of actions. Possible re-designs include the cryostat flanges
(there is
only one spare available at the moment) and the rotating valve/pulse
tube
assembly. This evaluation is still pending.
The proposed plan for modifications as discussed
during
the July 2006 meeting between CEA and CFHT has not yet been finalized.
In view
of the fact that the timescale for such re-designs is expected to be
long, SAC
recommends that actions be taken to accelerate the process.
·
WIRCam
Since the last SAC meeting, WIRCam has become
part of the normal CFHT operations. Very few problems have occurred,
but the
weather has been so bad that not many observations have been carried
out. A
press release for the first results from WIRCam is being prepared.
Changes in readout and reset procedures have
led to improved guiding. Problems with
high noise levels (30-40 ADU) in some amplifiers were solved leading to
a noise
level below 15 ADU but in consequence a single frame readout time is
likely to
be limited to 1.4 secs. Furthermore, to avoid a problem with a gradient
appearing on the science readout, it was decided that the arrays would
be read
twice, with the first read discarded. This provides more than the
necessary
settling time but is an easy fix for the moment. Therefore the times
between
integrations cannot be smaller than 2.8 secs at the moment.
Excellent image quality continues to be
achieved but there have been some problems with the focus of one array
with
respect to the others. This problem is probably due to a varying
thickness of
the substrate on the arrays through which the light has to go through
as the
arrays are back illuminated. This is presently being investigated but
the most
likely solution will be a tilt of the entire mosaic. SAC notes that the
new
Bracket Gamma filter has arrived. The full set of filters is now being
offered
to observers. This semester, 9 filters were requested (there are only 8
slots
available). After discussions between SAC and the members of the
executive that
were present, it was decided that by opening the instrument at a
strategic
moment (not at the beginning of the semester) to change one filter, the
problem
would be solved.
SAC applauds the fact the Elixir pipeline is
now ready. This pipeline is for the time being based on the IDL
software
package to provide flexibility but requires a few manual procedures. Some of the 2005B data have been reduced
using this pipeline and distributed to users.
The automation of the astrometry and of image de-trending
remains to be
done and is planned for the end of 2006. What is the best type of flat
field to
use also remains to be decided upon.
·
ESPaDOnS
The new fibre bundles have been received by
CFHT. It was determined that they had a very similar throughput as the
old ones
before they were damaged. The original 50% throughput shortfall of the
entire
instrument (0.3 mag) is still not understood and is currently being
investigated. No progress has been made yet on the problem of the
wavelength
shift occurring during a night. The resolution, which is not quite as
high as
previously announced, is probably the best that can be expected. This is still being looked into.
The problem of polarization cross-talk has
mostly been solved by replacing the collimator triplet lens. The
problem was
due to birefringence of the lens due to thermal stressing. The original
lens as
well as the first replacement suffered this problem but the second
replacement
lens did not.
Queue observing with ESPaDOnS has still to be
looked into since the bad weather has barely left sufficient time to
fully test
the 2-instrument (MegaPrime and WIRCam) queue mode.
However, we note that at the present time, the observers are
invited to share the allocated nights in order to improve the observing
efficiency. This effective ²mini-queue² is organised by the observers and
has been working well up to now.
SAC notes
that the semester observing plan of the LS and its impact on PI
programs was
sent, as requested, by the SG to the TACs but re-emphasize that it
should be
sent early enough to give the TACs time to evaluate its impact.
Therefore the
schedule should be sent no later than 1-2 weeks after the proposal
deadline.
The LS
progress report documents sent to the SAC before each meeting are
extremely
useful to evaluate the status of the survey. Therefore these documents
should
be made available to SAC members in good time in order for SAC to be
able to
give them proper consideration before and at the meeting.
SAC finds
the way in which the SG has consulted the LS community on the issue of
opening
a new field for the Wide component extremely satisfactory. SAC is happy
that
this will provide the necessary flexibility to help insure that the
core
program of the Wide component be completed on time.
SAC
acknowledges that the first World Wide Release of the LS has now been
defined
as T0003 and that a date has been set for its release (16 February
2007).
In their report to SAC, the SG states that the
Wide component core program (u/2, g, r/2, i, z/2) will be completed by
the end
of 2007B and that the SNLS may be ramping down at that time. This
satisfies the
SAC recommendations made during the mid-term review of the LS. SAC
requests a
plan for LS observations up to the expected end-date of the survey, at
the end
of 2008A.
SAC recognises that within the current
allocation, not all the planned observations will be completed. The SG
states
that at least three more semesters are necessary to complete the survey
as
originally planned. SAC recommends that a review of the state of the
survey
take place in one year from now at the time of the next user’s meeting.
In particular, to fully understand the impact if
an extension were not granted, SAC would like to see presented during
this
review a quantitative analysis of what scientific goals of the original
project
will be compromised as a consequence.
Letter from the
Canada-France
Ecliptic Plane Survey
team
SAC
discussed the letter sent by the CFEPS team to the agency’s
representatives,
the chair of the Board and of the SAC concerning a possible
re-introduction in
the LS of some parts of the Very Wide component.
SAC notes that the bad weather on Mauna Kea is
persisting and that in consequence the average number of validated
hours per
night has not been increasing. Therefore the previous arguments (see
recommendation number 9 in the mid-term review) remain valid and
therefore SAC
recommends that the VW-component or part of it not be re-introduced.
SAC extensively discussed WIRCam Large programs, taking into account input from members of the committee that are also members of the TAC. Discussions included making more specific the nature of large programs as well as a possible delay for the next call for proposals.
SAC
recommends that a second call for WIRCam large programs go forward
as planned next August for semester 2007A. SAC re-emphasizes that TACs
should
commit, at the time of acceptance, observing time for the number of
semesters
required to complete the program.
SAC discussed the evaluation process of joint
Canada-France proposals, including the effect of the pressure on the
various
instruments that is different in each country. TAC members also
explained that
the procedures that had been derived to evaluate joint WIRCam Large
Programs
which involved ranking of the proposals by each TAC and then a
telephone
communication between both chairs to discuss the WIRCam Large programs
did not
work in practice because of the difficulty in finding common dates for
the TAC
meetings.
SAC requests that CFHT make the statistics on the pressure on different instruments publicly available.
SAC
proposes that joint Canada-France proposals should be re-discussed
by the TAC members who are also SAC members and that they should reach
a final
ranking at the time of the SAC meeting.
Christian Veillet presented to SAC an analysis of the 8-night rule, the history of its implementation, its observance and impact in the past ten semesters. SAC was pleased to learn that in order to achieve the best scientific use of the telescope and respect the TACs ranking as much as possible, the Director took measures, such as allocating D-time to increase the length of a run, to insure that not many programs had to be excluded because of this rule. Only 10 nights in the past 10 semesters had to be excluded. Many of the concerns at the origin of the 8-night rule are still valid today.
SAC believes that in the immediate future, CFHT
should take full
advantage of the three main instruments (MegaPrime, WIRCam and
ESPaDOnS) and
should simplify as much as possible its operations for the sake of a
higher
efficiency. Therefore, in view of the small demand from users for MOS
and
Gecko, SAC restates its recommendation that these two instruments be
de-commissioned in one year. The 8-night rule has no effect on this
recommendation.
DDT time
Following a request
by SAC one year ago, Christian Veillet has prepared and presented to
the Board
last fall a report of the usage of the Directors Discretionary Time
(DDT) at
CFHT. This was presented to SAC. The origin of the DDT as well as its
usefulness in general was described and an account for 2005 was
provided. There are 10 DDT nights in total
each
semester and 3 of those have been given to the CFHTLS. Furthermore,
some of
these nights are used to prepare the scientific case for the future
instruments
or to solve tricky problems with the night allocations of the agencies.
The
general impression is that this is a positive measure and that the
numbers of
DDT nights is not excessively high even though the pressure on the
telescope is
quite strong. Therefore, SAC thinks that this measure should continue
and that
an account of the usage of DDT should be provided to SAC each year at
the fall
meeting.
Pierre Martin presented the QSO report. Queue observations are proceeding very
well and the
validation rate is now above 88% for A+B programs on MegaPrime. For
WIRCam, the
rate is still low in this early stage but most of the time was lost to
commissioning and engineering.
SAC is pleased to hear that a new queue
observer has been hired to help carry out the observations, which are
intensive
now that 2 instruments are being extensively used in queue. This has
greatly
helped to reduce the pressure on the staff.
Christian Veillet presented an update on the goals and the metrics the observatory is using to keep track of failures. The percentage of clear sky time lost to failure per run is close to 4%, which is the present goal set by the management. This represents a very small amount of failures and SAC congratulates the staff for this achievement. SAC was informed that the plan is to attempt to decrease this to eventually reach 2% by 2010.
Large
surveys in the future
SAC discussed a
possible second round of large surveys for MegaPrime and WIRCam after
the
completion of the Legacy Survey and found that it was premature to make
a
recommendation at this stage. Committee members would like to seek
input from
the CFHT users’ community on this issue.
SAC recommends that, at the next CFHT users
meeting, an agenda item be included to discuss a second round of large
surveys.
Other
instruments in
2008-2010
SAC discussed the possibility of issuing a call for
proposals to the
community for the possible usage of outside instruments as Guest
Instruments in
the 2008-2010 time period. SAC does not
believe that it is wise at this point to issue a call for ideas for the
use of
outside instruments in that period. SAC believes that the pressure will
still
be high on the three main instruments and therefore sees no need to
complicate
further the operations and add more duties for the staff.
VASAO
Work on Fly-Eyes has been progressing smoothly.
We note that the integration with PUEO should start in May and that
on-sky
tests should take place during the second semester.
VASAO is currently undergoing a feasibility
study and results should be presented to SAC at the next meeting.
Performance
modelling of the expected Strehl ratios, field size and laser
guide-star flux
have been carried out and the necessary modification to the AO Bonnette
and to
the telescope are being made.
Christian Veillet
presented a brief update of the recent developments of VASAO. Also, in
early
January 2006, a VASAO mailing list was created and a call for
scientific input
from the CFHT community was made and many ideas were received. SAC would like a summary to be presented at
the next SAC meeting. A feasibility study for VASAO is now underway and
SAC
would also like to be informed on the outcome of this study at the next
meeting.
CFHT12K
Christian Veillet
informed SAC that no buyers have been found for CFHT12K but that the
detector
(or part of it) can perhaps be used as a test detector for VASAO.
Vice-Chairmanship
Pierre-Alain Duc has
been designated by INSU as Vice-Chair of the SAC for a term effective
immediately and ending on 31 December 2007.
CFHT Users meeting
The next users
meeting should take place in France next spring. It was proposed to
organise it
in Marseille or in the surroundings and SAC approves this. The most
probable
dates for this meeting are 9, 10, 11 May 2007 and the SAC meeting
should be
held on the 12-13 May in Cassis.
Next meeting
The next SAC meeting will be held in Waimea on the 9-10 November 2006 with the summit visit on the 8 November.